88.1% of“836”Investment and Project Construction Plan Has been Fulfilled in Chenzhou City

2015-03-20

 

How is everything going on for the “836” investment and project construction plan? It was learned from Chenzhou Development and Reform Commission that about 90% of the plan has been fulfilled and it was estimated to be fully completed in the end of 2015.

 

According to the data, till the end of 2014, the total fixed-asset investment of Chenzhou city was accumulated to be 704.43billion yuan, covering 88.1% of the target set for“twelfth five-year plan”; the investments placed on 32 main projects were amounted to 352.31billion yuan, covering 91.7% of the targets; and the investments placed on 664 key items were accumulated to 414.404billion yuan, covering 87.9%.

 

In early 2011, Chenzhou Municipal Party Committee and Chenzhou Government listed “836” investment and project construction plan which referred to 800billion yuan investment, 32 main projects, and 664 key items construction need to be handled during the period of“twelfth five-year plan”. Analyzed from the key data, the main tasks concerned for the plan have been over fulfilled in the first four years of “twelfth five-year plan”, so the whole “836”plan can be fully completed in the end of 2015.