The groundbreaking ceremony for the Chenzhou Power Plant project of Guoyue Group was held on August 28.
The project, located in Meitian Town of Yizhang County, plans to build a 1x700,000 kW ultra-supercritical circulating fluidized bed coal-fired power generation unit, as well as its auxiliary, office and living facilities, with a dynamic investment of 3.431 billion yuan.
At the same time, flue gas desulfurization, denitrification, and dust removal facilities will be constructed. The annual utilization hours of the unit are about 4,000 hours, and the annual power generation after commissioning will be 2.8 billion kWh, with an output value of about 1.26 billion yuan.
The project will drive the further development of the upstream and downstream industrial chains, strengthen the energy supply in the region, and boost new-quality productivity in Hunan Province.
Chinese source: rednet