Chenzhou Zhongbo Broadcasting Station to be completed

2025-02-08

Workers were busy binding steel bars and an excavator was doing foundation work for protective slopes at the relocation project site of Chenzhou Zhongbo Broadcasting Station on February 5.

 

01.png

 

The project covers a total area of about 104 mu (about 6.93 hectares), with a total construction area of about 2,598 square meters. It includes multiple functional areas such as the transmitter room, comprehensive business building, and logistics auxiliary building. It will be equipped with advanced program source transmission, switching, monitoring, listening and monitoring systems to create a fully automated and intelligent system for the entire station, with complete building electromechanical systems and site facilities to be built. 
 
After completion, it will provide stronger technical support and guarantee for the broadcasting and television communication in Chenzhou, which will further enhance the local broadcasting and television communication capacity and service level.
 
02.png
 
Since it started construction, it has successively completed the construction of infrastructure such as water, electricity, and roads, as well as pile foundation engineering, earthwork protection engineering, and the main construction of the transmitter room. 
 
As of now, the main structure of the transmitter room has been capped. The foundations of the comprehensive and logistics buildings have been completed and passed third-party inspections. The basketball court and internal roads have also been hardened. Two launch platforms have been lowered to elevation. The uphill road and launch platform support piles have been completed. 
 
“After work resumption, we immediately began to dismantle the indoor scaffolding, and will start decoration and equipment installation. The entire project will be finished at the end of March,” said Zhang Yaoming, representative of the construction party of the project.
 
Chinese source: rednet